It has been almost a year since my  presentation on August 1, 2012, but my journey for answers began over 25 years ago. Beginning in 1987, I have documented noncompliance issues afflicting the Harrisburg Steam Generating Faculty (HSGF), renamed the Harrisburg Materials, Energy, Recycling and Resource Recovery Facility (Facility) in 1992.

On March 11, 1974,   Site A was filled beyond capacity. Six years later, on January 10, 1980, the Office of Attorney General (AG) filed an Equity Complaint with the Commonwealth Court against the City of Harrisburg. The AG alleged the HSGF continued to deposit incinerator residue at Site A and failed to have Site B properly prepared.

On September 12, 1978, DER issued Permit No. 100992 to the City of Harrisburg for the operation of Pit B-1. Almost seven years later on July 10, 1985, the Pennsylvania Department of Resources (DER) notified the City of Harrisburg. The existing condition of residue disposal Sites A and B-1 causes concern for the potential impact on human health and the environment.

On June 27, 1986, the DER issued a Notice of Violation (NOV) for the Citys failure to close Site A and maintain a leachate collection system. Similarly, Site B was issued a NOV for filling B-1 (Mt. Ashmore) beyond capacity and failing to maintain a leachate treatment system or diversion channel.

The City of Harrisburg replied on August 17, 1986: The reality and economics of the situation are such that it will be virtually impossible to remove all the ash from both sites to the originally permitted levels. 

On December 20, 1988, the City agreed to close Site A by March 15, 1989, (15 years after the pit was full), and pay a $25,000 penalty.

The ash residue analysis conducted by Skelly and Loy on September 28, 1987 supported the contention that the ash residing in Pit A and B-1 is hazardous. DER conducted ash residue analysis on May 23, 1985 and August 8, 1985 which concluded that the ash residing in Pit A and B-1 is hazardous.

The City of Harrisburg did not dispose of the hazardous ash in a “hazardous” waste landfill. Harrisburg claimed an exemption to hazardous treatment for the ash residue allegedly found in the Solid Waste Management Act is identical to the language in the Resource Conservation and Recovery Act (RCRA). Changing the label does not change the content, but the cycle of playing regulatory catch-up began in the 1980s.

The fly, bottom, and combined ash streams generated by the HSGF during the years 1985 and 1987 was technically and legally classified as “hazardous” waste under the EP toxicity test used by the Environmental Protection Agency (EPA) and the DER to determine the hazardousness of waste. The HSGF disposed of the ash in onsite pits designated Pit A and Pit B Neither pit was qualified to receive hazardous waste.

Last year – sitting at this table I  asked the same questions I asked back in 1987.

  1. Have these legacy environmental issues identified over 30 years at Pit-A and Pit-B been fully and completely remediated?
    If so, does the County posses the manifests and where can citizens obtain the documentation, and current status of environmental and groundwater monitoring?
  2. The facility is a de facto hazardous waste site. Who or what is ultimately liable and responsible for maintaining, monitoring and remediating any future cleanup?
    Does the chain of custody end with City residents or County taxpayers?
  3. The reuse value as well as the taxable value of this property is linked to the cleanup standard.
    Will this 20 acre property be cleaned up to a Brownfield or Greenfield standard?
  4. Is there an external, segregated funding mechanism in place to ensure the cleanup of Harrisburg Materials, Energy, Recycling and Resource Recovery Facility is implemented?
    How much is in the fund and who controls it? Are the investment or withdraw limitations?

It  has been wild ride searching, requesting and trying to track down records related to the presence of hazardous waste and the status of an environmental review prior to the sale of the Harrisburg Materials, Energy, Recycling and Resource Recovery Facility. You can pick up the scent of the hazardous  waste trail in 1990.

On April 20, 1990 it was DERs position that certain batches of ash generated at the HSGF can be characterized as hazardous under state law and must be disposed of as such.

On October 19, 1990,  the City argued  the legal definition of hazardous waste, but admitted, Indeed in nearly every technical aspect, the B-2 site is essentially the equivalent of a hazardous waste land fill both under current and proposed Pennsylvania regulations. Safety concerns will also be served by the elimination of the the need to transport the ash great distances to a hazardous waste treatment disposal facility.

Also the City  argued …that safe disposal should be the main focus and that safety is best deserved by disposal at the Citys B-2 site, that of disposing of the ash as hazardous waste is exorbitant and a threat to the existence of an environmentally beneficial facility… (Howard J. Wein of Klett, Leiber Rooney & Schorling, October 19, 1990.)

The argument is as follows: Although the waste on site may be hazardous waste, it is legally defined as something else. Rather than risk the health and safety of people along the transportation routes, it is more prudent to store the waste on site at a facility not designed to store hazardous waste. The economic cost outweighs the the health and safety of those who live and work next to the site.

If you accept this argument, beware of the precedent:  Substitute the term hazardous waste for nuclear waste and you have an identical argument for storing radioactive waste on site at Three Mile Island.

Unfortunately, my inquires have not yielded definitive answers or remain unanswered. After spending several days in the DEPs document room and making Right to Know Requests to the City Receiver and the Harrisburg Authority, it appears that there is a probability the portions of the ash pits contain hazardous waste.

The City of Harrisburgs position was identical to the stance adopted by James Warner, Executive Director of  Lancaster County Solid Waste Management Authority (LCSWMA). Gil Smart from the  Intelligencer Journal reported on June 2, 2013.

LCSWMA Executive Director James Warner, dismissed concernsabout potential environmental problems on the incinerator site. Inthe late 1980s, both the state Department of EnvironmentalResources and federal Environmental Protection Agency raised thepossibility of soil or groundwater contamination due to the disposalof ash on the site. However, in response to questions from oneactivist last year, a Pennsylvania Department of EnvironmentalProtection spokesman said none of the waste buried on the site washazardous. Last week Warner agreed, insisting there are nohazardous waste liability issues.”

Mr. Warner told me that the Supreme Court issued a decision in City of  Chicago vs EDF  that exempts municipal solid waste ash from being hazardous waste. In that 7-2 ruling on May 2, 1995, the Supreme Court interpreted this identical language of the claimed exemption to specifically not include ash residue that, but for the claimed exemption, would be classified as hazardous. The  Court held, “An ash can be hazardous, even though the product from which it is generated is not, because in the new medium the contaminants are more concentrated and more readily leachable.”

The City of Harrisburg, in its capacity as owner of the HSGF, filed an amicus brief  supporting the City of Chicago.

The legal argument is that waste generated by resource recovery facilities are exempted from regulation as a hazardous waste even if they are hazardous waste.

Changing the label does not change the content.

The Harrisburg Authority’s  (HA) did respond to my request  relating to on-site hazardous waste – after a 30 day delay for legal review. Our response is that no records responsive to your request exist to provide documents, governmental communications, release forms and work papers that codify and confirm and document that the HSGF and its environs are not classified as as a hazards waste site.  To our knowledge, the HSGF and its environs are not classified as a hazardous.  (Karen McKillip, The Harrisburg Authority, Document Manager/Right to Know officer, November 26, 2012.)

Not an affirmation but a plausibility deniability defense . The Response was copied to four different attorneys and Shannon Williams.

DEP approved a Major Permit Modification for Change of Ownership for Permits Nos. 100992 and 100759 A and B Ash Disposal sites which transferred liability to the Harrisburg Authority. I am still searching for the Environmental Impact Statement required by law and referred to as a Form D Environmental Assessment.  In March 2003, William Cluck filed a Notice of Appeal with the DEP and the Harrisburg Authority  arguing the required Form D Environmental Assessment was not completed. {{1}}

Was an EIS conducted in 2003? If so, do you have a copy? It is possible these documents exist but I was unwilling to pay $9,150 to cover the RTK Requests. The DEP informed that was the copying estimate for the cost of the documents in a 12 page rejection letter sent on November 28, 2102 by Assistant Regional Director Robert Conrad.

I am asking you as County Commissioners for your assistance in locating an environmental review of the site.  In the absence of an environmental review, the regulations require the permitee to conduct a site assessment. The permitee of record assumes most of the liabilities, but the former owner(s) of of a facility may still be liable.

Jack Lausch, Facility Director, wrote to Commissioner Haste on September 25, 2012 regarding the issues I raised on August 1, 2012. He prefaced his comments by saying the time frame of 1972-1991 is not an era where the Authority has institutional knowledge with which to provide our response about activities at that time…

Mr. Lausch stated:

The new permit holder assumes all liabilities from the date when the original permit was first issued. With respect to the statements  required under 25 PA Code 271.221 regarding liabilities and responsibilities the permitee must assume, the permitee assumes  liabilities related to past operations. DEP does not allocate liabilities  between parties. However, DEPs approval of permit reissuance to a new entity does not limit the liability, duty or obligation of past permits under the law as specified in 25 PA Code 271.221(c). {{2}} (Bold face type added.)

What is the date of the original permit?

While stating a lack of institutional knowledge at the outset of his letter, Mr. Lausch inserted footnote {{3}}. Lausch stated, We see no need to respond to Mr. Epstein s unilateral assertion that the facility is a hazardous waste site. Our silence is not not an should not be perceived as agreement.

I was not copied.

So who is liable and where are the facts?

I asked the Authority on October 23, 2012:  Please provide the name, location, and addresses of the  corporations, entities and/or government bodies that are legally liable for cleanup and remediation costs.

On October 26, 2012, Authority acknowledged they received the request. The HA needed additional time due to the need for a legal review of the information requested which precluded a responses within five (5) business days and detailed than an additional thirty (30) days to process the request. (Karen M. McKillip, Harrisburg Authority.)

On November 26, 2013, I was informed, Youre request is denied. A Right to Know request may request Public Records. Your request does not request Public records, but instead, requests, Names, locations and addresses.

We are at critical mass. The question remains: Will the sale of the  Harrisburg Materials, Energy, Recycling and Resource Recovery Facility facility located in Dauphin County generate an Environmental Assessment.

In addition to securing an environmental assessment prior to the sale of the facility, it would be prudent to insist on the issuance of  permit care   the post closure care of the hazardous waste landfill located  at the Harrisburg Materials, Energy, Recycling and Resource Recovery Facility. {{4}}

_____  

[[1]] 271.126.Requirement for environmental assessment.

(a)Except as provided in subsection (b), an application for a municipal waste disposal or processing permit shall include an environmental assessment on a form prescribed by the Department.

(b)The following permit applications do not require an environmental assessment unless the Department determines that the facility may have a significant effect on the environment:

(1)Permit applications for the beneficial use of municipal waste.

(2)Permit applications for the processing of municipal waste under Subchapter I (relating to beneficial use).

(3)Permit modification applications that are not for major modifications under 271.144 (relating to public notice and public hearings for permit modifications).

(c)For facilities which have previously been subject to the environmental assessment process, the Department will limit the scope of review under that process to the following:

(1) Proposed modifications to the facility.

(2) Changes in the areas covered by the assessment that have occurred [[1]]

[[2]]Ibid.[[2]]

[[3]]Ibid.[[3]]

[[4]]Dauphin County Commissioners Meeting, August 3, 2011: Notification from DEP advising that they issued a draft permit to ArcelorMittal Steelton, LLC for the post closure care of their HWM-1 hazardous waste landfill located at 214 S. Front Street. DEP is accepting written comments from the public and ArcelorMittal on the draft permit for 45 days from the date of the letter (July 29, 2011).[[4]]